Why your plans always run late (a 1994 study)
34 days predicted. 56 days it took. Here is what the research says to do about it.
Fact-checked by Diana

Contents
- What the students predicted, and what actually happened.
- 37 students. One question. Three guesses.
- The same pattern appeared in everyday tasks.
- Large projects have a long record of running late.
- Planners look ahead and set the past aside.
- Three things the research supports.
- Find your planning number
- Questions and answers
What the students predicted, and what actually happened.
The planning fallacy is the tendency to expect our own plans to go smoothly, even when similar plans have run late.
In 1994, psychologists Roger Buehler, Dale Griffin and Michael Ross put it to the test. They tracked 37 students through the final semester of their honors thesis.
Here is what they found, why it happens, and what the research says helps.
37 students. One question. Three guesses.
The students were asked one question:
“When will you finish your thesis?”
Each student gave three estimates of their completion time: a best estimate, an optimistic estimate assuming everything went as well as it possibly could, and a pessimistic estimate assuming everything went as poorly as it possibly could. The researchers then recorded the day each thesis was actually completed.

Best guess: 34 days. The students finished after about 56. Only 30% made it by the date they had predicted.
Optimistic guess: 27 days. Only 11% finished by then.
Worst case: 49 days. Even in the worst case they could imagine, fewer than half (49%) finished by that date.
The same pattern appeared in everyday tasks.
In a second study, participants named tasks they intended to complete within the following week. These included school assignments and everyday tasks around the home.
For school assignments, they predicted about 6 days. The work took about 11. For everyday tasks, they predicted about 5 days. Those took about 9.
Only 37% of the assignments and 43% of the everyday tasks were finished within the predicted time.
Large projects have a long record of running late.
The researchers opened their paper with three well-known examples of projects that ran far past their schedule.

The Sydney Opera House. Estimated in 1957 to be finished in early 1963 for A$7 million. A scaled-down version opened in 1973 at a cost of A$102 million.
Montreal’s Olympic stadium roof. In 1969 the mayor promised a retractable roof for the 1976 Games and said the venture “can no more have a deficit than a man can have a baby.” The roof was in place in 1989, 13 years late.
Canada’s transcontinental railway. Promised for 1881. The last spike was driven in 1885.
Planners look ahead and set the past aside.
So why does the pattern repeat?
In a further study, participants thought aloud while making their predictions. Their attention went mainly to future scenarios: how the work would proceed, step by step.
Little attention went to how similar tasks had turned out before.
When participants did recall earlier delays, they attributed them to causes with three things in common:
- External
- The cause lay in circumstances, not in the person.
- Temporary
- The cause was unlikely to occur again.
- Specific
- The cause belonged to that one task, not to tasks in general.
If every earlier delay is treated as an exception, there is no reason to adjust the next estimate.
The effect was named in 1979 by psychologists Daniel Kahneman, winner of the 2002 Nobel Prize in economics, and Amos Tversky, a professor of psychology at Stanford University. Buehler and colleagues describe it as a confident belief that one’s own project will proceed as planned, even while knowing that most similar projects have run late.
Three things the research supports.
Research points to three habits that help you guess better. Linking your prediction to past experience removed the optimistic bias. Asking someone else helps, because observers predicting for other people did not make the same mistake. Splitting the task into steps helps too, since the time people gave the separate steps added up to more than the time they gave the whole task.
Look at last time. When participants were instructed to connect their predictions to relevant past experiences, the optimistic bias was eliminated.
Ask someone else. Observers predicting for other people did not make the same mistake. They overestimated how long the tasks would take, and they used past experience more.
Split it into steps. Other researchers found that the time people allocated to a task’s individual steps added up to more than the time they allocated to the task as a whole. List the steps before you estimate.
Find your planning number
Five steps, spread over the week.
- Pick three quests.
- Before you guess, write down how long the last similar quest really took.
- List the steps for each quest, then write your guess.
- If you can, ask a friend how long they would expect it to take you.
- Time the real thing. On Friday, compare.
your own planning number. Use it to plan next week.
Questions and answers
What is the planning fallacy?
The planning fallacy is the tendency to expect our own plans to go smoothly, even when similar plans have run late. It was named in 1979 by psychologists Daniel Kahneman and Amos Tversky.
What did the 1994 thesis study find?
Roger Buehler, Dale Griffin and Michael Ross tracked 37 students finishing their honors thesis. Their best guess was 34 days, but they finished after about 56, and only 30% made it by the date they had predicted.
Why do plans keep running late?
When making predictions, people focus mainly on how the work will go step by step and pay little attention to how similar tasks turned out before. Earlier delays get treated as external, temporary and specific, so the next estimate is not adjusted.
How can you make better time estimates?
The research supports three things: connect your prediction to how long similar tasks took last time, ask someone else to predict for you, and list the task's steps before you estimate.